City Hall Facilities Upgrade
Minutes:
The Manager reported that the Political Party Rooms would be painted in August.
A Quantity Surveyor had been appointed for the basement facilities upgrade project and once costs had been finalised it was envisaged that procurement could proceed in September. It was estimated that works would take four months with a view to completion by year end.
The toilets in the basement were in the process of being upgraded.
Order: Report Noted.